Machine spare parts · Urgent
Production line down, and a certificate to get before the part can ship
The problem. A South African machine supplier had a blow-moulding line standing still in East Africa after a servo motor failed. They needed a new motor, a drive already programmed so no engineer had to fly out, and the power and control cables, and they needed to know the cost fast.
The catch. The East African destination country will not clear servo equipment without a pre-shipment Certificate of Conformity (PVoC), and that needs lab test reports to three IEC standards. The factory's own supplier could not provide them. Wrong paperwork or a mismatched model number means goods held at the port while the line stays down. On top of that, the original drive series had been discontinued.
How the funnel ran
- Factories from our archive of suppliers already checked on earlier jobs for this client.
- Technical check: exact motor model and rating, drive compatibility (including a current replacement for the discontinued drive), cable connectors, programming support, test-report availability, lead time, export experience, stock.
- Quotes compared in one format, quoted ex-works so the client could add his own freight.
- 1 supplier appointed, and an independent test lab lined up to issue the reports and certificate for motor and drive in one batch.
What made the difference. When the factory said it could not supply the test reports, we did not stop: we found a lab that could, and asked for the test and the certificate to be done together. Packing, HS codes and crate size were settled up front, so the client could ask for courier costs while the paperwork was still moving. Model numbers had to match exactly on the test reports, the nameplate, the invoice and the packing list, and nothing ships until the certificate is issued.
What you can take from this. Compliance belongs in the quote, not at the border, and “the factory can't” is where sourcing starts, not where it ends.